Overview
According to tender and planning information disclosed by industry outlet Century Energy Storage, the Jilin-to-Beijing transmission project built around an ±800 kV DC ultra-high-voltage corridor runs more than 1,000 kilometres through Jilin, Inner Mongolia, Liaoning, Hebei, Tianjin and Beijing. It is expected to be fully commissioned by 2029, delivering clean power from Jilin and Heilongjiang directly to Beijing. Companion generation would be located in Baicheng and Songyuan in Jilin and Daqing in Heilongjiang, with a planned scale of roughly 14.64 GW: no less than 7 GW of wind, 5 GW of solar, 2.64 GW of peak-shaving coal power, plus 1.8 GW of four-hour storage. Public information indicates at least three groups have so far received 10.84 GW of renewable quotas, paired with 2.64 GW of peak-shaving coal capacity.
Published tender lots show how the build-out is being sequenced. One feasibility-study lot for the 5.32 GW companion power package of the Songliao clean-energy base’s north-China transmission corridor covers 2x660 MW of coal power, 2.35 GW of wind and 1.65 GW of solar, with 600 MW of four-hour electrochemical storage proposed; the tender requires the feasibility report within 60 working days of contract signing. Bundling renewables, supporting coal capacity and storage into a single feasibility study reflects a shift in cross-region delivery: from single-resource renewable bases toward integrated design of generation, storage and flexibility.
Regional energy planning is converging in the same direction. A 15th Five-Year Plan for high-quality development of industrial parks issued by Anhui province supports source-grid-load-storage integration and direct green-power connections as the backbone of zero-carbon parks, backed by carbon-dual-control rules, an energy industrial internet platform and local consumption pathways; related guidance sets a floor that a project’s annual self-consumed power should be no less than 60% of total available generation. Thousand-kilometre interprovincial delivery on one end and on-site park consumption on the other both point to a common shift: renewables moving from pure capacity expansion toward building absorption capability.
Background & Interpretation
1. Industry and Policy Context
The spatial mismatch between wind and solar resources in the north, west and northeast and load centres in the east and centre is the structural driver of UHV transmission. As desert-base projects come online at scale, new frictions have emerged around channel utilisation, peak-shaving pressure in receiving grids and renewable curtailment. Policy has responded by listing new power grids, virtual power plants, new-type storage and computing-power-grid coordination as priority investment areas under the 15th Five-Year Plan, with the National Energy Administration targeting 300 GW of new-type storage by 2030. Approval and construction of cross-region corridors has consequently broadened from a single line into a system of transmission channels, companion generation, peaking capacity and storage. Dual demand in receiving regions such as Beijing for green power and reliability provides clear market pull for long-distance direct supply.
2. Core Drivers and Underlying Mechanism
The 14.64 GW mix deserves unpacking. 7 GW of wind and 5 GW of solar supply the bulk energy; 2.64 GW of peak-shaving coal covers nights, calm periods and extreme weather; 1.8 GW of four-hour storage, about 7.2 GWh, smooths output, tracks the delivery curve and provides frequency and grid-forming support. The combination is necessary because a UHV DC corridor targets high utilisation hours and a stable delivery profile while wind and solar are inherently variable. Without flexible resources the line must either be curtailed or create curtailment and peak-shaving gaps at the receiving end. Four-hour duration maps to shifting energy into the evening peak, while peaking coal provides multi-day and seasonal backstop. Putting all three into one feasibility study treats energy, capacity and flexibility as a single product designed together rather than approved separately and stitched together later. The 60% self-consumption floor for direct green supply is the same logic expressed on the load side: lock in offtake before adding capacity.
3. Market Structure and Industry Chain Impact
For wind, solar and storage equipment, multi-gigawatt companion packages mean large-scale orders for high-capacity turbines, efficient modules, large-format cells and grid-forming converters, and because technical routes are fixed at feasibility stage, suppliers with system-integration and grid-code compliance capabilities are better placed to enter the chain. For coal power, the role of 2.64 GW of peaking units shifts from baseload energy to capacity and flexibility services, with returns depending more on capacity payments and ancillary markets than on utilisation hours. For grid operators and design institutes, a corridor crossing six provincial jurisdictions involves sending-receiving coordination, dispatch-right allocation and transmission tariff setting, making it more complex than intra-provincial work. For Beijing, direct green supply improves the local generation mix and carbon accounting while raising demands on power-flow distribution and contingency reserves. Upstream storage cells, power conversion systems and UHV converter-valve equipment stand to benefit from this system-level build cadence.
Implications & Outlook
Near term, the project remains at feasibility and quota-allocation stage; full commissioning in 2029 implies equipment tenders and construction will be released in batches, with study progress, quota placement and approval timing as leading indicators. Three variables matter over the medium term: whether capacity-leasing and capacity-compensation mechanisms for companion storage deliver stable return expectations; whether capacity tariffs and ancillary pricing for peaking coal cover fixed costs at low utilisation; and how sending and receiving provinces settle green-power environmental attributes, transmission tariffs and consumption-responsibility weights. Long term, if interprovincial direct supply and on-site park consumption mature in parallel, renewable assessment may shift from installed capacity toward deliverable energy and dispatchable capability, turning storage and flexibility from a cost item into a distinct value segment.
Takeaways for Industry Participants
Equipment and system-integration firms should prioritise grid-forming capability, four-hour duration adaptation and grid-code compliance, and engage at feasibility and scheme-design stage rather than competing on price alone at tender; cross-province differences in delivery cycles, payment schedules and local supporting conditions also warrant assessment. Power investors should rebuild return models for peaking generation and storage around capacity payments, ancillary services and green attributes instead of a single energy-price assumption. Parks and large energy users can benchmark the self-consumption floor by first mapping load profiles and dispatchable resources, then sizing direct green connections to avoid capacity outrunning actual absorption. For researchers, tracking such projects is more informative through companion-power structure, storage duration and delivery curves than through voltage class or line length alone.